NISTA’s PFI Reset guidance, published on 16th November 2026, marks a practical shift in how the government approaches mid-life and expiring PFI contracts.
Since 2021 Curshaw has asserted that resetting underperforming or strained projects needs a jointly owned, evidence-based review agreed by both parties, rather than an exercise focused on exploiting deductions. Through continued engagement that approach is now reflected in NISTAs published Reset Routemap which closely mirrors our proposed methodology developed for complex project resets, Counterpoint.
NISTA developed the guidance utilising input from the public and private sectors. As a founding adviser of the Association of Infrastructure Investors in PPPs (AIIP), Curshaw contributed to that dialogue, and we welcome how much of the market’s feedback the final suite reflects, from both sides of the contract.
Our findings here, build out on our earlier article, “We were correct and the industry is now headed in the right direction”. It sets out where NISTA’s guidance aligns with the positions we have published since 2021, how Counterpoint delivers the framework in practice, and where the remaining operational questions sit for live projects.
From published positions to government guidance
Many organisations across the public and private sectors have advocated a more collaborative approach to PFI management. Comparing the positions Curshaw has set out since 2021 against NISTA’s November 2026 suite shows substantial alignment on the core principles of reset:
| Curshaw’s published position | NISTA’s published guidance |
|---|---|
| Start with a jointly agreed baseline review, rather than a forensic search for deductions | Each party completes a Project Stocktake, with a joint exercise recommended, and the Reset Routemap begins by sharing results |
| Agree a single version of the truth before taking corrective action | The stocktake is structured to surface where views differ, so both parties understand the other’s position before deciding next steps |
| Proportionality: not every project requires a full reset | Reset is reserved for issues too material to be resolved through day-to-day contract management |
| Reset is a joint endeavour, not a unilateral process imposed on one party | Reset delivers better outcomes when it is jointly led rather than driven by one party alone |
| Under-management and information asymmetry exist on both sides of the contract | The authority’s own resourcing and contract management are in scope, with under-management recognised as an issue |
| Adviser incentives do not always align with long-term project stability | Advisers must not assume the role of Senior Responsible Owners (SROs) or SPV directors, nor unilaterally determine the course of a reset |
| A reset must hold through to expiry | Delivery includes a dedicated stage to embed best practice and transition back to business as usual |
NISTA describes reset as an opportunity rather than a sign of failure, and advises authorities to exhaust a joint approach before considering unilateral action. It is also clear that not every project needs a reset. Proportionality is built into the guidance from the outset.
Counterpoint: mapped to the Reset Routemap
NISTA has defined the framework. Counterpoint is an established delivery method structured around four core principles: joint endeavour, proportionality, fixed-fee certainty and long-term sustainability.
| Counterpoint stage | What Curshaw delivers | NISTA Routemap equivalent |
|---|---|---|
| 1. Joint appointment | Engaged jointly by both parties, or by one party with a collateral warranty to the other, so our responsibility is to the project itself | Joint stocktake and a jointly led reset process |
| 2. Survey and review | Independent condition surveys sized to need based on an objective assessment of data, alongside a review of the service specification and payment mechanism against a consistent standard | Project Stocktake, Building Blocks and the Asset Condition Playbook |
| 3. Remedy, rectify and improve | A shared definition of what good looks like, transparent rectification plans and agreed governance | Reset set-up, planning and implementation |
| 4. Embed and sustain | Software-enabled performance reporting and periodic independent assurance through to contract expiry | Embedding best practice and moving on |
The joint appointment model addresses a common structural flaw in PFI advisory work: an adviser paid solely by one party naturally optimises for that client’s commercial position. An adviser accountable to the project can give objective technical and commercial findings to both sides. We have applied this joint model in the health sector, advising an NHS Trust and its SPV together on adapting facilities management delivery.
Where the guidance should go further
The core framework now reflects a position both sides of the market can support, but several operational areas remain partly resolved or open to interpretation. It's fair to say that some of these gaps are in the nature of arms length advice rather than Government mandate. However we would urge further clarity of that guidance framework for the reasons suggested here and to ensure greater consistency of approach:
| Open point | Current status in guidance | Practical implication for live projects |
|---|---|---|
| Relief during reset | The Asset Condition Playbook permits agreed relief during rectification, whereas the reset guidance says relief should not be assumed | Parties must still negotiate the scope, triggers and duration of any payment mechanism relief project by project |
| Payment mechanism adjustments | Dedicated guidance is still in development | Projects changing operational practices need a defined bedding-in period, so new working methods do not immediately trigger fresh deductions |
| Financial model access | NISTA explains why authorities need visibility of the financial model, without resolving how to manage its commercial sensitivity | Parties need clear protocols on what financial data is strictly necessary to share and how confidentiality is protected |
| SPV discretion and supply chains | Only partly addressed in the published suite | Reset agreements must account for where decision-making authority sits across SPVs, funders, investors and FM subcontractors |
| Programmatic coordination | No cross-departmental programme to sequence resets or manage survey capacity is set out | Without central coordination, simultaneous resets risk bottlenecks in technical surveying and specialist advisory capacity |
| Joint procurement rules | The Playbook outlines a joint tender process but does not explain how it fits with public procurement rules | One route: Counterpoint can be engaged by a single party with a collateral warranty for the benefit of the other, so the adviser’s responsibility is still to the project itself |
Why advisers must see both sides
Public-private partnerships are long-term operational contracts, not zero-sum transactions. Contracting authorities need reliable asset performance, statutory compliance and a clean handback at expiry. SPVs, investors and service providers need deliverable specifications, consistent contract interpretation and predictable cash flows. In practice, these objectives depend on the same outcome: a stable, functioning asset.
When advisers have only ever represented one side of the market, they tend to treat a reset as a zero-sum negotiation. Curshaw’s clients include funds, project owners and directors, and contracting authorities, and our team brings experience across more than 95 PFI projects, covering expiry preparation, handback delivery and post-PFI transition. Our breadth of experience helps both parties reach workable agreements faster.
How we deliver reset work
NISTA notes that parties may need specialist support and advice, without prescribing how that support should be structured. Curshaw works to two clear commercial rules.
Fixed-fee delivery. Open-ended time-and-materials billing puts the focus on finding more problems rather than fixing them. We work on a fixed-fee basis, so costs are predictable and controllable. Authorities gain budget certainty, SPVs have a clear end point, and the team stays focused on resolution.
Commercially led, with legal advice tightly scoped. Most issues identified by NISTA, such as weak governance, unreliable performance data and misaligned working practices, are operational and commercial, not legal. When a reset becomes legally led either by legal advisors or because of their advice, positions harden and routine correspondence is drafted with an eye on future adjudication. Our RPD approach (Review and Reset, Prepare, Deliver) starts from an objective, standards-based assessment of project performance with an evidential basis. Where formal contractual interpretation is needed, it should be referred to the parties’ legal advisers on a tightly defined brief, while the reset itself remains commercially led.
Starting with the Project Stocktake
With the policy framework established, the priority is execution across mid-life and expiring contracts. NISTA’s recommended starting point is the Project Stocktake. Where it shows more work is needed, Curshaw has three established ways in:
Reset assessment and support. An independent assessment of how the project operates and how the interfaces between the parties are managed (governance, reporting and contract administration), with a service improvement plan.
Project operational review. A RAG rating against Curshaw’s best practice standard, with a single-page dashboard for senior stakeholders and a prescriptive action plan. It is designed to sit at the interface between the contracting parties.
Counterpoint. A full joint reset, from joint appointment through to sustaining the fix to expiry.